Smoke Extract Fan Selection: Temperature Class and Documents

Smoke extract fan selection requires more than finding a high temperature label. Define the fan duty, fire scenario and interfaces with the rest of the system together. Buyers also need to check how the documents for the offered model cover the required temperature and operating duration.

Define the role in the fire scenario

Required airflow and pressure come from the smoke control design. State whether the fan provides main extraction, replacement air or impulse movement as a jet fan. Normal ventilation and emergency operation may involve different conditions.

Building geometry, air inlets, discharge locations and activation sequence affect the system. Do not select temperature class or fan quantity from floor area alone. Use the project design criteria, applicable national requirements and the assessment of the competent design team.

Read temperature class and duration together

Read class codes such as F300 or F400 within the applicable standard definition and the product’s declared performance. A “300/400°C” label alone does not establish that the required duration and all model options are covered. Verify temperature, duration and application conditions in the same document set.

For illustration, assume a project specification requires operation at 400°C for 120 minutes. This is an example requirement, not a recommendation for every project or a performance declaration for a Voltvent product. Match the exact offered configuration to evidence applicable to that requirement.

Understand the scope of EN 12101-3

EN 12101-3 addresses product characteristics and test and assessment methods for powered smoke and heat control fans. Impulse or jet fans used for smoke control are also within its scope. Establish the applicable standard edition and any additional national conditions for the project.

A fan product document alone does not establish suitability of the connected ducts, dampers, power supply or the complete building fire design. A general ventilation performance curve does not replace evidence for operation at fire temperature. Product assessment and system design are complementary tasks.

Match the document scope to the exact model

Compare model code, diameter or size, motor and speed arrangement, mounting orientation and any accessory restrictions with the document scope. Do not assume an unlisted modification is covered. Check document number, revision, issuer and any validity conditions.

Request the performance declaration and supporting certification records required in the applicable market. For the European market, the relevant construction products framework and transition provisions can affect which declaration and assessment documents apply. A CE mark alone does not complete every project document check. Assess other countries’ requirements separately.

Coordinate the fan with the complete system

Coordinate emergency power, control sequence and permitted speed control operation within the project. Installation conditions for the fan, ducts, dampers and connections must be compatible. Do not assume settings used for normal ventilation are automatically suitable for emergency duty.

Jet fan thrust may be expressed in N, whereas main extract volume flow uses units such as m³/h. These quantities are not interchangeable. Consider jet fan layout and main extraction capacity together with the intended smoke movement strategy.

Define acceptance and maintenance records early

The handover file should identify the product, applicable technical documents, installation and operating instructions, and commissioning criteria. Define the functions, airflow and pressure points and control scenarios to be checked on site. These checks do not replace laboratory fire performance testing.

Set maintenance responsibilities and inspection intervals in line with applicable requirements and product instructions. If the motor, controls or mounting change, review the document scope and project assessment again. Do not replace missing technical evidence with a general statement that a product is suitable.

Share the project duty, required temperature and duration, duty point and model information with Voltvent for a technical review.

Contact Sales

Privacy Preference

Your privacy, your choice.

We use essential browser storage to remember your preferences. Optional external content, including the office map, only loads with your permission.

You can use the website with essential storage only and change your choice at any time under Privacy preferences in the footer. Read our for details.